This ground-up automotive facility was built to support Meineke’s operational standards and provide a modern, efficient space for vehicle maintenance and customer service. The 4,000-square-foot build features multiple service bays, a front retail lobby, and integrated warehouse storage, creating a seamless connection between customer-facing and back-of-house operations.
Project Duration:
- Timeline: 6 months
- Completion Date: June 2025
“Kalb Construction delivered on every promise for our Meineke build at 5th and Deer Springs. Their team managed the project efficiently, maintained excellent communication, and kept quality high from start to finish. The project came in on budget and was completed more than two weeks ahead of schedule, a rare and welcome outcome in today’s construction environment.”
Project Highlights
Challenges Overcome
The team faced a delayed start caused by overlap with another project that required a full redesign. Once the permitted drawings were issued, Kalb moved quickly to mobilize, ensuring all contracts, submittals, and coordination efforts were executed on time to keep the project moving forward.
Schedule Insight
The project maintained consistent momentum and was completed within the planned six-month timeline. Strong communication and early coordination kept the schedule steady despite initial setbacks.
Budget Outcome
The final cost landed slightly above the initial estimate due to specific design and scope requirements that limited value engineering options. Throughout construction, cost transparency and proactive management ensured the client remained informed and confident in every decision.