The District at Green Valley Ranch
Overview
Kalb Construction completed a 17,617-square-foot ground-up shell building at The District at Green Valley Ranch, one of Henderson’s most active commercial destinations. The structure was designed for retail and business use, providing a flexible footprint for future tenants while maintaining architectural continuity with the surrounding development.
Project Duration:
- Timeline: 12 months
- Completion Date: October 2022
"Kalb was organized, flexible, and worked through every challenge. They kept us on schedule and delivered exactly what we needed."
Project Highlights
Challenges Overcome
This high-traffic location required tight coordination with utility providers, city inspectors, and multiple subcontractors to maintain progress and site safety. Kalb managed all work from slab prep through final painting and storefront installation.
Schedule Insight
The project was completed in 12 months. Preconstruction planning and early trade buy-in helped the team avoid costly delays and keep the site on schedule despite its complexity.
Budget Outcome
Value engineering during the design phase helped the client reduce overall spending while preserving the quality and visual cohesion of the building. Kalb delivered the final product on budget and ready for tenant build-outs.